[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388967":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388967,172,1,"单选题","我公司承包了一个工程，项目总预算是100W，管理储备是20万，应急储备是20W，下列正确的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","管理储备是用来应对已知未知风险的应急时间或应急资金。",false,{"key":16,"text":17,"correct":14},"B","应急储备是用来应对未知未知风险的应急时间或应急资金。",{"key":19,"text":20,"correct":21},"C","在项目进行中，项目经理可以动用应急储备。",true,{"key":23,"text":24,"correct":14},"D","BAC=100W","BAC=项目总预算-管理储备=100-20=80W，应急储备是用来应对已知未知风险的应急时间或应急资金。管理储备是用来应对未知未知风险的应急时间或应急资金。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]