[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388965":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388965,172,1,"单选题","一份完整的项目绩效报告应该包含的内容有：项目的进展和执行情况、成本的使用情况、团队成员的绩效情况、 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","变更后的项目计划、项目存在的问题及解决措施",false,{"key":16,"text":17,"correct":14},"B","变更后的项目计划、对项目的预测",{"key":19,"text":20,"correct":14},"C","干系人沟通需求、需求变更",{"key":22,"text":23,"correct":24},"D","项目存在的问题及解决措施、对项目的预测",true,"绩效报告包括完成的活动、成果、里程碑、发现的事件与问题。状态报告用来报告关键的信息，包括但不限于下列内容：① 当前的状态；② 本报告期的重要成果；③ 计划的活动；④ 事件。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]