[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388964":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388964,172,1,"单选题","已知某综合布线工程的挣值曲线如下图所示：总预算为1230万元，到目前为止已支出900万元，实际完成了总工作量的60%，该阶段的预算费用是850万元。按目前的状况继续发展，要完成剩余的工作还需要 （ ） 万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","330",false,{"key":16,"text":17,"correct":14},"B","492",{"key":19,"text":20,"correct":21},"C","600",true,{"key":23,"text":24,"correct":14},"D","738","根据题干，可判定计算的目标是按当前的CPI来计算剩余工作的预计完工成本。按目前CPI状况继续发展，剩余工作的预计完工成本=（BAC-EV）\u002FCPI，其中BAC=1 230，EV=1230?60%=738，CPI=EV\u002FAC=738\u002F900=0.82。则剩余工作的预计完工成本=（1230-738）\u002F0.82=600",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]