[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388960":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388960,172,1,"单选题","（ ） 不是项目成本估算的输入。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目进度管理计划",false,{"key":16,"text":17,"correct":14},"B","项目管理计划",{"key":19,"text":20,"correct":21},"C","项目成本绩效报告",true,{"key":23,"text":24,"correct":14},"D","风险事件","项目成本估算的输入包括项目进度管理计划、项目管理计划以及风险事件。项目成本绩效报告不是项目成本估算的输入，而是成本控制的输入。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]