[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388959":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388959,172,1,"单选题","以下关于项目成本控制的叙述中， （ ） 是不正确的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本控制可提前识别可能引起项目成本基准变化的因素，并对其影响",false,{"key":16,"text":17,"correct":14},"B","成本控制的关键是经常并及时分析项目成本绩效",{"key":19,"text":20,"correct":21},"C","成本控制的单位一般为项目的具体活动",true,{"key":23,"text":24,"correct":14},"D","进行成本控制是要防范因成本失控产生的各种可能风险","项目成本控制必须和项目进度结合起来才能进行有效的控制。成本控制必须识别可能引起项目成本基准计划发生变动的因素，并对这些因素施加影响，以保证该变化朝着有利的方向发展。监督费用实施情况，发现实际费用和成本计划的偏差，并找出偏差的原因，阻止不正确、不合理和未经批准的费用变更。成本控制是项目管理的重要活动不只是个人的活动。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]