[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388957":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388957,172,1,"单选题","某信息系统集成项目采用净值分析技术进行成本控制，假设当前状况数据如下表所示，则该项目的CPI、EA C、当前项目的状态分别是 （46） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.8，12 500元，进度滞后且成本超支",true,{"key":16,"text":17,"correct":18},"B","0.8，10 000元，进度提前且成本超支",false,{"key":20,"text":21,"correct":18},"C","1.25，12 500元，进度滞后且成本低于预算",{"key":23,"text":24,"correct":18},"D","1.25，10 000元，进度提前且成本低于预算","此题没有说是否是典型还是非典型偏差，当采用EAC=ac+（bac-ev）\u002Fcpi这个公式时，A选项符合要求。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]