[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388955":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388955,172,1,"单选题","关于系统建设项目成本预算，下列说法中不正确的是 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本总计、管理储备、参数模型和支出合理化原则用于成本预算",false,{"key":16,"text":17,"correct":14},"B","成本基准计划是用来衡量差异和未来项目绩效的",{"key":19,"text":20,"correct":21},"C","成本预算过程对现在的项目活动及未来的运营活动分配资金",true,{"key":23,"text":24,"correct":14},"D","成本基准计划计算的是项目的预计成本","成本预算过程将总的项目成本估算分配到各项活动和工作包上，来建立一个成本的基线。成本预算是一个计划过程，并不为未来的运营活动分配资金。本题的A、B、D三项是对的，选项C是不正确的。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]