[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388954":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388954,172,1,"单选题","某项目在进行进度计划管理时，计算得出CPI小于1，SPI小于1,该项目是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本节约，进度落后",false,{"key":16,"text":17,"correct":18},"B","成本超支，进度落后",true,{"key":20,"text":21,"correct":14},"C","成本节约，进度超前",{"key":23,"text":24,"correct":14},"D","成本超支，进度超前","CPI小于1成本超支，SPI小于1进度落后",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]