[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388952":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388952,172,1,"单选题","假设某项目任务已进行了充分细化分解，任务安排及完成情况如下图，已获价值适用50\u002F50规则（活动开始执行即获得一半价值），则下图中项目监控点的PV、EV、BAC分别为 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","PV=4200,EV=3000,BAC=5200",false,{"key":16,"text":17,"correct":14},"B","PV=4200,EV=3300,BAC=4600",{"key":19,"text":20,"correct":21},"C","PV=3600,EV=3300,BAC=5200",true,{"key":23,"text":24,"correct":14},"D","PV=3600,EV=3000,BAC=4600","PV是计划工作量的预算，将虚线前的预算金额加起来PV=400+1000+1200+400+600=3600，即可。BAC是总预算，将图中所有预算相加，BAC=400+1000+1200+400+600+600+1000=5200。所以选C。EV从图中只能估算，肯定是大于400+1000+1200+400+部分虚线后的已完成部分>3000小于3600。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]