[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388951":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388951,172,1,"单选题","某软件开发项目，预算为40万元，计划在40个工作日内完成，当项目进行到第30个工作日时，项目经理对项目进行了绩效评估，结果是：项目完成当期计划进度的70%，花费了23万，按此绩效还需投入大约 （ ） 万元才能完成该项目。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","12",{"key":19,"text":20,"correct":14},"C","19",{"key":22,"text":23,"correct":24},"D","21",true,"ETC=(BAC-EV)\u002FCPI=(BAC-EV) ×AC\u002FEV=(40-21) ×23\u002F21=20.81万元。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]