[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388946":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388946,172,1,"单选题","项目Ⅰ.Ⅱ.Ⅲ.Ⅳ的工期都是三年，在第二年末其挣值分析数据如下表所示。按此趋势，项目 （ ） 应最早完工。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Ⅰ",false,{"key":16,"text":17,"correct":18},"B","Ⅱ",true,{"key":20,"text":21,"correct":14},"C","Ⅲ",{"key":23,"text":24,"correct":14},"D","Ⅳ","这是最基本的计算，必须掌握。求出四个SPI=EV\u002FPV中的最大值。SPI(I)=1000\u002F1200=0.83SPI(II)=1300\u002F1200=1.08SPI(III)=1250\u002F1200=1.04SPI(IV)=1100\u002F1200=0.92Max（0.83，1.08，1.04，0.92）=1.08，故SPI(II)最大。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]