[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388945":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388945,172,1,"单选题","（ ） 一般不属于项目绩效报告的内容",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","团队成员考核",false,{"key":16,"text":17,"correct":14},"B","项目预测",{"key":19,"text":20,"correct":14},"C","项目主要效益",{"key":22,"text":23,"correct":24},"D","变更请求",true,"绩效报告包括：项目的进展和执行情况、成本的使用情况、团队成员的绩效情况、状态报告、进展报告、预测报告、项目存在的问题及解决措施。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]