[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388943,172,1,"单选题","以下关于成本基准特点的叙述中，不正确的是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按时间分段计算，用做度量和监督成本绩效的基准",false,{"key":16,"text":17,"correct":18},"B","成本基准反映整个项目生命期的实际成本支出",true,{"key":20,"text":21,"correct":14},"C","按时段汇总估算的成本编制而成",{"key":23,"text":24,"correct":14},"D","通常以S曲线的形式表示","成本基准是用来量度、监督与控制项目实际成本绩效的预算。这个预算是按阶段来编制的，将按时段估算的成本加在一起，即可得出成本基准，通常以S曲线形式显示。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]