[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388942":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388942,172,1,"单选题","在某项目进行的第三个月，累计计划费用是25万元人民币，而实际支出为28万元，以下关于这个项目进展的叙述，正确的是：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","提供的信息不全，无法评估",true,{"key":16,"text":17,"correct":18},"B","由于成本超支，项目面临困难",false,{"key":20,"text":21,"correct":18},"C","项目将在原预算内完成",{"key":23,"text":24,"correct":18},"D","项目计划提前","根据题干得到信息,项目当前的PV=25. AC=28因为PV是计划要做的工作的预算, 而AC是实际完成的工作的实际花费pV与AC无法直接进行比较，故答案选A",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]