[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388940":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388940,172,1,"单选题","成本控制过程主要内容不包括（ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将目的成本分配到项目的各项具体工作上",true,{"key":16,"text":17,"correct":18},"B","识别可能引起项目成本基准计划发生变动的因素，并对这些因素施加影响",false,{"key":20,"text":21,"correct":18},"C","对发生成本偏差的工作包实施管理，有针对性地采取纠正措施",{"key":23,"text":24,"correct":18},"D","对项目的最终成本进行预测","成本预算就是把项目总预算按要求分配到每一个wbs工作包上，因此A不正确。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]