[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388938":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388938,172,1,"单选题","某项目成本偏差（CV）大于0，进度偏差（SV）小于0，则该项目的状态是 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本节省、进度超前",false,{"key":16,"text":17,"correct":18},"B","成本节省、进度落后",true,{"key":20,"text":21,"correct":14},"C","成本超支、进度超前",{"key":23,"text":24,"correct":14},"D","成本超支、进度落后","挣值分析是测量绩效最常用的方法。挣值涉及计算每个活动的4个关键值：计划值（PV）、实际成本（AC）、挣值（EV）、剩余工作的成本估算（ETC）。CV=EV-AC>0，表明项目实施处于成本节省状态；SV（SV=EV-PV\u003C0，表明项目实施落后于计划进度。因此该项目的状态是“成本节省、进度落后”。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]