[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388932":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388932,172,1,"单选题","超出项目经理控制的成本增加因素，除了存款利率、贷款利息和税率外，还包括（ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目日常开支的速度和生产率",false,{"key":16,"text":17,"correct":14},"B","项目日常开支的速度和工期拖延",{"key":19,"text":20,"correct":14},"C","项目补贴和加班",{"key":22,"text":23,"correct":24},"D","原材料成本和运输成本",true,"超出项目经理控制的成本增加因素，除了存款利率、贷款利息和税率外，还包括原材料成本和运输成本。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]