[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388922":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388922,172,1,"单选题","按照沟通计划安排，项目经理在某财务控制点要根据挣值分析理论向财务总监提交绩效报告，下列绩效报告内容正确的是 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按照控制账户中财务指标，对CPI CV BAC进行计算和分析并提出措施",false,{"key":16,"text":17,"correct":14},"B","根据控制点基线，对CPI CV SPI SV BAC进行计算和分析并提出措施",{"key":19,"text":20,"correct":14},"C","根据控制点基线，对CPI CV SPI SV ETC进行计算和分析并提出措施",{"key":22,"text":23,"correct":24},"D","按照控制账户中财务指标，汇报财务状态、进展报告，进行状态分析",true,"由题干中得知项目经理是在财务控制点向财务总监提交绩效报告，所以应该按照控制账户中的财务指标汇报财务状态和进展报告，进行状态分析。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]