[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388916":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388916,172,1,"单选题","项目Ⅰ、Ⅱ、Ⅲ、Ⅳ的工期都是三年，在第二年末其挣值分析数据如下表所示，按照趋势最早完工的应是项目 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Ⅰ",false,{"key":16,"text":17,"correct":18},"B","Ⅱ",true,{"key":20,"text":21,"correct":14},"C","Ⅲ",{"key":23,"text":24,"correct":14},"D","Ⅳ","由计算结果可知项目II进度提前最多，成本与计划持平。故按照趋势最早完工的应是项目II。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]