[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388915":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388915,172,1,"单选题","项目经理在执行过程中收集了工作绩效数据，EV=3万，PV=6万，AC=4万，当前SPI和CPI分别是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","SPI=50%，CPI=75%",true,{"key":16,"text":17,"correct":18},"B","SPI=50%，CPI=67%",false,{"key":20,"text":21,"correct":18},"C","SPI=67%，CPI=50%",{"key":23,"text":24,"correct":18},"D","SPI=67%，CPI=5%","公式SPI=EV\u002FPV=3\u002F6=50%，CPI=EV\u002FAC=3\u002F4=75%",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]