[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388913":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388913,172,1,"单选题","根据以下布线计划及完成进度表，在2010年6月2日完工后对工程进度和费用进行预测，按此进度，完成尚需估算（ET C）为 ：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","18000元",false,{"key":16,"text":17,"correct":18},"B","36000元",true,{"key":20,"text":21,"correct":14},"C","20000元",{"key":23,"text":24,"correct":14},"D","54000元","根据题目给出的信息可知，EV=10000 ，AC=18000按此进度，说明是典型情况，则ETC=（BAC-EV）\u002FCPI =（30000-10000）\u002F10000\u002F18000 = 36000",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]