[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388911":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388911,172,1,"单选题","下列选项中，项目经理进行成本估算时不需要考虑的因素是 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","企业环境因素",false,{"key":16,"text":17,"correct":14},"B","员工管理计划",{"key":19,"text":20,"correct":21},"C","盈利",true,{"key":23,"text":24,"correct":14},"D","风险事件","成本估算的输入包括：企业环境因素、组织过程资产、项目范围说明书、工作分解结构、WBS字典、项目管理计划（包括进度管理计划、员工管理计划、风险事件）。故不需要考虑盈利因素。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]