[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388908":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388908,172,1,"单选题","下列选项中，项目经理进行成本估算时不需要考虑的因素是 （ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","人力资源",false,{"key":16,"text":17,"correct":14},"B","工期长短",{"key":19,"text":20,"correct":14},"C","风险因素",{"key":22,"text":23,"correct":24},"D","盈利",true,"成本估算需要根据活动资源估算中所确定的资源需求（包括人力资源、设备和材料等）以及市场上各种资源的价格信息来进行。具体而言，项目成本同项目所耗用资源的数量、质量和价格有关；同工期长短有关；同项目质量结果有关；同项目范围的宽度和深度有关。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]