[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388903":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388903,172,1,"单选题","某正在进行中的项目，当前的PV=2200元、EV=2000元、AC=2500元，该项目的CPI和成本绩效是 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.20；实际成本与计划的一致",false,{"key":16,"text":17,"correct":14},"B","0.80；实际成本比计划成本要低",{"key":19,"text":20,"correct":21},"C","0.80；实际成本超出了计划成本",true,{"key":23,"text":24,"correct":14},"D","1.25；实际成本超出了计划成本","SV = EV - PV = 2000 - 2200 = -200 \u003C 0",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]