[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388901":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388901,172,1,"单选题","完成某信息系统集成项目中的一个最基本的工作单元A所需的时间，乐观的估计需8天，悲观的估计需38天，最可能的估计需20天，按照PERT方法进行估算，项目在26天以后完成的概率大致为 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","8.9%",false,{"key":16,"text":17,"correct":18},"B","15.9%",true,{"key":20,"text":21,"correct":14},"C","22.2%",{"key":23,"text":24,"correct":14},"D","28.6%","期望工期=（8+4?20+38）\u002F6=21 标准差=（38-8）\u002F6=5 26天与21天之间为1个标准差（而非±1个标准差），16天到26天之间为±1个 标准差，根据正态分布规律，故16天到26天之间完成的概率为68.26%，26天以后完成的概率=（1-68.26%）\u002F2=15.87%。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]