[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388899":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388899,172,1,"单选题","下图是某项目的剪线图（时间单位：周），其关键路径是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1-4-6-8-10-11",false,{"key":16,"text":17,"correct":14},"B","1-3-9-11",{"key":19,"text":20,"correct":21},"C","1-4-9-11",true,{"key":23,"text":24,"correct":14},"D","1-2-5-7-11","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]