[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388894":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388894,172,1,"单选题","依据下面的项目活动网络图中，该项目历时为 （34） 天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","11",{"key":19,"text":20,"correct":14},"C","13",{"key":22,"text":23,"correct":24},"D","18",true,"本题考查的是关键路径，活动历时时间最长的那条路径是关键路径，其工期为项目的总工期。从本题可以算出，最长的路径的工期是18天，所以D为参考答案。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]