[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388892":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388892,172,1,"单选题","在下面的项目网络图中（时间单位为天），活动B的自由时差和总时差分别为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0、0",false,{"key":16,"text":17,"correct":18},"B","0、1",true,{"key":20,"text":21,"correct":14},"C","1、0",{"key":23,"text":24,"correct":14},"D","1、1","本工作的自由时差-等于紧后工作最早开始时间与本工作最早完成时间差的最小值。 本工作的总时差=本工作最迟开始时间-本工作最早开始时间 或者 本工作的总时差=本工作最迟完工时间-本工作最早完工时间，所以活动B的自由时差和总时差分别为0和1， 正向推导、反向推导得出B的ES为2，EF为5，LF为6，C的ES为5，EF为9，LS为6，LF为10.所以B的自由时差=C的ES-B的EF=5-5=0，B的总时差=B的LS-B的ES=3-2=1",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]