[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388890":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388890,172,1,"单选题","（ ）是借助网络图和各活动所需时间（估计值），计算每一项活动的最早或最迟开始和结束时间。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A. CPM",true,{"key":16,"text":17,"correct":18},"B","CM",false,{"key":20,"text":21,"correct":18},"C","资源平衡",{"key":23,"text":24,"correct":18},"D","资源平滑","CPM（关键路径法）是借助网络图和各活动所需时间（估计值），计算每一项活动的最早或最迟开始和结束时间。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]