[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388887":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388887,172,1,"单选题","项目经理小李对一个小项目的工期进行估算时，发现开发人员的熟练程度对工期有较大的影响，如果都是经验丰富的开发人员，预计20天可以完成；如果都是新手，预计需要38天；按照公司的平均开发速度，一般26天可以完成。该项目的工期可以估算为 （ ） 天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","26",false,{"key":16,"text":17,"correct":18},"B","27",true,{"key":20,"text":21,"correct":14},"C","28",{"key":23,"text":24,"correct":14},"D","29","根据PERT计算：（最乐观工期+4×最可能工期+最悲观工期）\u002F6，从题目中找出最乐观工期=20，最悲观工期=38，最可能工期=26，代入PERT公式，计算出（20+4×26+38）\u002F6=27",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]