[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388885":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388885,172,1,"单选题","某项目预计最快12天完成，最慢36天完成，21天完成的可能性最大。公司下达的计划是18天完成，要使计划完成的概率达到50%，在计划中需要增加 （ ） 天应急时间。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4",true,{"key":16,"text":17,"correct":18},"B","6",false,{"key":20,"text":21,"correct":18},"C","8",{"key":23,"text":24,"correct":18},"D","22","三点估算法求出期望工期=（12+4 ? 21+36）\u002F6=22，而期望工期是按时完工概率的50%，所以如果要18天完成，需要增加22?18=4天。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]