[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388884":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388884,172,1,"单选题","某软件项目已经到了测试阶段，但是由于用户订购的硬件设备没有到货而不能实施测试。这种测试活动与硬件之间的依赖关系属于：",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","强制性依赖关系",false,{"key":16,"text":17,"correct":14},"B","直接依赖关系",{"key":19,"text":20,"correct":14},"C","内部依赖关系",{"key":22,"text":23,"correct":24},"D","外部依赖关系",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]