[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388882":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388882,172,1,"单选题","制定进度计划过程中，常用于评价项目进度风险的技术是 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","关键路径分析",false,{"key":16,"text":17,"correct":14},"B","网络图分析",{"key":19,"text":20,"correct":21},"C","PERT分析",true,{"key":23,"text":24,"correct":14},"D","关键链分析","PERT分析，是根据活动工期的三种可能性，计算出活动平均工期的一种方法。最常用的PERT计算公式为：（最乐观工期+4最可能工期+最悲观工期）\u002F6。结合标准差公式、方差公式，可计算出不同工期范围内完工的机会大小（某段时间范围内完成活动的可能性），常用于评价有关项目进度的风险。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]