[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388880":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388880,172,1,"单选题","（ ）是一种基于历史数据和项目参数，使用某种算法来计算成本或工期的估算技术",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","类比估算",false,{"key":16,"text":17,"correct":14},"B","三点估算",{"key":19,"text":20,"correct":21},"C","参数估算",true,{"key":23,"text":24,"correct":14},"D","储备分析","参数估算是一种基于历史数据和项目参数，使用某种算法来计算成本或工期的估算技术。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]