[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388879":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388879,172,1,"单选题","一项任务的最早开始时间是第3天，最晚开始时间是第13天，最早完成时间是第9天，最晚完成时间是第19天。该任务（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在关键路径上",false,{"key":16,"text":17,"correct":14},"B","有滞后",{"key":19,"text":20,"correct":14},"C","进展情况良好",{"key":22,"text":23,"correct":24},"D","不在关键路径上",true,"因该任务有10天的浮动时间，可以断定它不在“关键路径上”。关键路径上的任务浮动时间皆为0。题干中没有交代该项目是处于哪个阶段，也没有交代该任务的基准进度和预算，因此不能断定它“有滞后”，还是“进展情况良好”。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]