[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388878":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388878,172,1,"单选题","下图为某工程进度网络图，节点1为起点，节点11为终点，此工程最快 （ ） 天完成",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","18",false,{"key":16,"text":17,"correct":18},"B","28",true,{"key":20,"text":21,"correct":14},"C","22",{"key":23,"text":24,"correct":14},"D","20","按照这样的过程求解4个参量数组，最后比较活动ai的最早开始时间和最晚开始时间，两者相同的即为关键活动，关键活动所在的路径就是关键路径。 本题中AOE网的关键路径为1—3—5—8—9—10—11，最大路径长度为28。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]