[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388876":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388876,172,1,"单选题","下图是某项目的剪线图（时间单位：周），其关键路径的工期是（ ）周。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","14",true,{"key":16,"text":17,"correct":18},"B","12",false,{"key":20,"text":21,"correct":18},"C","11",{"key":23,"text":24,"correct":18},"D","13","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]