[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388873":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388873,172,1,"单选题","某监理单位承担了一个信息系统工程全过程的监理 工作在应用系统建设过程中，由于工期紧张，成本有限，监理工程师按照承建单位的进度计划严格进行跟踪检查，并要求承建单位对 A、 B、 C、D四个重要活动进行成本优化。监理工程师在检查承建单位项目经理的成本优化方案时，检查了如下网络图: 结合案例，如果全部活动均在它们各自的应急工期内完成，该项目工期为（请作答此空）和项目总成本为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","16",true,{"key":16,"text":17,"correct":18},"B","17",false,{"key":20,"text":21,"correct":18},"C","18",{"key":23,"text":24,"correct":18},"D","19","结合案例，如果全部活动均在它们各自的应急工期内完成，计算项目工期和项目总成本。项目工期：9+7=16周",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]