[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388871":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388871,172,1,"单选题","某项目工期为6个月，该项目的项目经理在第3个月末对项目进行了中期检查，检查结果表明完成了计划进度的90%，相关情况见下表（单位：万元），表中活动之间存在F-S关系。 如果按照当前的绩效EAC为（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","60.12",false,{"key":16,"text":17,"correct":18},"B","60.22",true,{"key":20,"text":21,"correct":14},"C","58.12",{"key":23,"text":24,"correct":14},"D","58.22","“按照当前绩效”说明当前的偏差是典型的，因此，ETC=（BAC-EV）\u002FCPI=50-21.6\u002F0.83=34.22；EAC=ETC+AC=34.22+26=60.22",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]