[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388870":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388870,172,1,"单选题","某监理单位承担了一个信息系统工程全过程的监理 工作在应用系统建设过程中，由于工期紧张，成本有限，监理工程师按照承建单位的进度计划严格进行跟踪检查，并要求承建单位对 A、 B、 C、D四个重要活动进行成本优化。监理工程师在检查承建单位项目经理的成本优化方案时，检查了如下网络图: 结合案例，如果全部活动均在它们各自的应急工期内完成，该项目工期为（ ）和项目总成本为（请作答此空）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","25.7",false,{"key":16,"text":17,"correct":14},"B","25.8",{"key":19,"text":20,"correct":21},"C","26.7",true,{"key":23,"text":24,"correct":14},"D","26.8","结合案例，如果全部活动均在它们各自的应急工期内完成，计算项目工期和项目总成本。项目总成本：62000+110000+45000+50000=267000元",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]