[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388867":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388867,172,1,"单选题","某项目工期为6个月，该项目的项目经理在第3个月末对项目进行了中期检查，检查结果表明完成了计划进度的90%，相关情况见下表（单位：万元），表中活动之间存在F-S关系。 “概要设计”活动的SPI为（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.2",false,{"key":16,"text":17,"correct":14},"B","0.3",{"key":19,"text":20,"correct":21},"C","0.4",true,{"key":23,"text":24,"correct":14},"D","0.5","概要设计活动的：EV=21.6-8-12=1.6；SPI=EV\u002FPV=1.6\u002F4=0.4。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]