[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388862":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388862,172,1,"单选题","项目进度网络图是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","活动定义的结果和活动历时估算的输入",false,{"key":16,"text":17,"correct":18},"B","活动排序的结果和进度计划编制的输入",true,{"key":20,"text":21,"correct":14},"C","活动计划编制的结果和进度计划编制的输入",{"key":23,"text":24,"correct":14},"D","活动排序的结果和活动历时估算的输入","项目进度管理是指确保项目准时完成所需的过程。 其主要过程有：①活动定义：②活动排序；③活动资源估算；④活动历时估算；⑤制订进度计划；⑥进度计划控制。 通过对项目活动进行排序可以得到项目进度网络图，由项目进度网络图找到项目的关键路径，从而制订项目的进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]