[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388861":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388861,172,1,"单选题","已知网络计划中，工作M有两项紧后工作，这两项紧后工作的最早开始开始时间分别为第16天和第17天，工作M的最早开始时间和最迟开始时间分别为第6天和第9天，如果工作M的持续时间为9天，则工作M的表述正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总时差为3天",true,{"key":16,"text":17,"correct":18},"B","自由时差为0天",false,{"key":20,"text":21,"correct":18},"C","总时差为2天",{"key":23,"text":24,"correct":18},"D","自由时差为2天","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]