[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388859":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},388859,172,1,"单选题","（ ）不是活动历时估算依据。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目范围说明书",false,{"key":16,"text":17,"correct":14},"B","活动资源需求",{"key":19,"text":20,"correct":14},"C","组织过程资产",{"key":22,"text":23,"correct":24},"D","项目进度计划",true,"活动历时估算的依据有：活动清单、活动清单属性、项目范围说明书、项目成本估算、活动资源需求、资源可用性、组织的过程资产和风险记录。 项目进度计划是活动历时估算过程之后的制定进度计划过程的交付物，不是活动历时估算过程的依据。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]