[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388858":3},{"question":4,"library":22},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":21},388858,172,1,"单选题","某监理单位承担了一个信息系统工程全过程的监理 工作在应用系统建设过程中，由于工期紧张，成本有限，监理工程师按照承建单位的进度计划严格进行跟踪检查，并要求承建单位对 A、 B、 C、D四个重要活动进行成本优化。监理工程师在检查承建单位项目经理的成本优化方案时，检查了如下网络图: 在正常工期下，如果将项目工期减少1周，则首先应该压缩哪个活动?",[11,14,16,19],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",true,{"key":20,"text":20,"correct":13},"D","因为C、D是关键路径活动，必须要压缩关键路径上的活动。",{"id":6,"name":23,"category":24,"favorite":25},"(高级)信息系统项目管理师","职业资格",0]