[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388857":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":22},388857,172,1,"单选题","某监理单位承担了一个信息系统工程全过程的监理 工作在应用系统建设过程中，由于工期紧张，成本有限，监理工程师按照承建单位的进度计划严格进行跟踪检查，并要求承建单位对 A、 B、 C、D四个重要活动进行成本优化。监理工程师在检查承建单位项目经理的成本优化方案时，检查了如下网络图: 该项目的关键路径为（）",[11,15,19],{"key":12,"text":13,"correct":14},"A","A. 开始AB 结束",false,{"key":16,"text":17,"correct":18},"B","B. 开始CD 结束",true,{"key":20,"text":21,"correct":14},"C","","结合案例，如果按照正常工期估计，写出项目关键路径，并计算项目工期和项目总成本。关键路径：开始 C D 结束",{"id":6,"name":24,"category":25,"favorite":26},"(高级)信息系统项目管理师","职业资格",0]