[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388854":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},388854,172,1,"单选题","某工程包括 A、 B、 C、 D、 E、 F、G七个作业，各个作业的紧前作业、所需时间、所需人数如下表： 整个工程至少需要 （ ） 人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","9",false,{"key":16,"text":17,"correct":18},"B","10",true,{"key":20,"text":21,"correct":14},"C","12",{"key":23,"text":24,"correct":14},"D","14","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]