[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388849":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},388849,172,1,"单选题","在进行进度安排时，PERT图不能清晰地描述（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","每个任务从何时开始",false,{"key":16,"text":17,"correct":14},"B","每个任务到何时结束",{"key":19,"text":20,"correct":21},"C","各任务之间的并行情况",true,{"key":23,"text":24,"correct":14},"D","各任务之间的依赖关系","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]