[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388847":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388847,172,1,"单选题","关键路径法是多种项目进度分析方法的基础。（ ） 是关键路径法的延伸，为项目实施过程中引入活动持续期的变化。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","PERT网络分析",true,{"key":16,"text":17,"correct":18},"B","甘特图",false,{"key":20,"text":21,"correct":18},"C","优先日程图法",{"key":23,"text":24,"correct":18},"D","启发式分析法","在PERT网络计划中，某些活动或全部工序的持续时间实现不能准确确定，适用于不可预知因素较多的，过去未曾做过的新项目或复杂项目，或研制新产品的工作中。PERT技术的理论基础是假设项目持续时间以及整个项目完成时间是随机的，且服从某种概率分布。PERT可以估计整个项目在某个时间内完成的概率。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]