[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-388846":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},388846,172,1,"单选题","某工程包括 A、 B、 C、 D、 E、 F、G七项工作，各工作的紧前工作、所需时间以及所需人数如下表所示（假设每个人均能承担各项工作），按此工期，整个工程最少需要 （ ） 人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","8",false,{"key":20,"text":21,"correct":18},"C","9",{"key":23,"text":24,"correct":18},"D","10","根据题意可画出带时标的双代号网络图如下图所示： 可识别出关键路径为：A—B—D—E—G工期为15天。调整非关键路径上的活动，使得 各路径上并行活动人数最少的方案如下图。 故该工程的工期应为15天。按此工期，整个工程最少需要7人。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]